Currently the same tests are performed for standalone, connect-test, connect-prod.
- One job should be for running the functional tests on a standalone deployment.
- One job to perform additional tests like several deployment methods (mp-hotfix, JSF UI install, ...) and compare the resulting server.
- Advanced testing should be in a third job.
This ticket is about creating the jobs and adapt the chain, even if some are still empty. This can be done in a later ticket.
Modifying the testing jobs will have an impact on the way we release the package. Upload to connect production server will be done in a new job.
- depends on
-
NXBT-1787 Make skeleton job and script for finalizing the HF release