Uploaded image for project: 'Nuxeo Platform'
  1. Nuxeo Platform
  2. NXP-13009

shutdown work manager before closing the repository

    XMLWordPrintable

    Details

    • Type: Task
    • Status: Resolved
    • Priority: Critical
    • Resolution: Fixed
    • Affects Version/s: 5.8
    • Fix Version/s: 5.9.5
    • Component/s: Core
    • Tags:
    • Sprint:
      Sprint 1(5.9.3), Sprint RepoTeam 5.9.4-1, Sprint RepoTeam 5.9.4-2, Sprint RepoTeam 5.9.4-3, Sprint RepoTeam 5.9.4-4, Sprint RepoTeam 5.9.5-1

      Description

      As part of the repository shutdown, we're trying to close all remaining session. So the thread pools managed by the work manager requires to be shutdown before.

        Attachments

          Issue Links

            Activity

              People

              • Votes:
                0 Vote for this issue
                Watchers:
                3 Start watching this issue

                Dates

                • Created:
                  Updated:
                  Resolved:

                  Time Tracking

                  Estimated:
                  Original Estimate - 2 days
                  2d
                  Remaining:
                  Remaining Estimate - 2 days
                  2d
                  Logged:
                  Time Spent - Not Specified